EXECUTION  STAGE (Ongoing Projects) - 17th JULY 2017
SI. No. Name of the Project   Admin Approval cost
(Rs Cr.) 
Agency Funding Source  Total Physical Progress      (%)   Physical Progress  
1 2 3 4 5 12 13
  WATER SUPPLY PROJECTS        
1 Water Supply Scheme - Phulwarisharif               24.70 M/s SMS - JP JV JnNURM-UIG 92% Water supply started in all zone.
Piple laying in the all five zones almost completed
Work almost completed
2 Water Supply Scheme - Bodhgaya                33.56 M/s SMC - JITF JV JnNURM-UIG 95% To be completed in 31 August  2017
3 Water Supply Scheme - Naubatpur                 0.98 M/s Gorur Infra Pvt. Ltd. STATE 60% Direct water supply started through stand post since October 2016
4 Water Supply Scheme - Jhanjharpur                 4.43 M/s Gorur Infra Pvt. Ltd. STATE 30% To be completed in 30 December 2017
  SEWERAGE TREATMENT PROJECTS        
1 Sewerage Treatment Scheme - Bodhgaya               95.94 Ramky Infrastructure JNNURM-UIG 85% Work is not in progress due to unavailbility of fund
2 Sewerage Treatment Scheme - Buxar               74.95 Tri-Tech Infrastructure NGRBA 38% Termination of Agreement is in process due to slow progress of project by contractor.
3 Sewerage Treatment Scheme - Hajipur             113.62 Tri-Tech Infrastructure NGRBA 27%
4 Sewerage Treatment Scheme - Begusarai               65.40 Tri-Tech Infrastructure NGRBA 14%
5 Construction of STP (43MLD) at Beur, Patna               68.16 M/s Voltas NGRBA   Contract Agrement is signed on 31.3.2017
6 Construction of Sewerage Network 180 KM  at Beur, Patna             225.77 M/s. L&T Construction NGRBA   Contract Agrement is signed on 30.3.2017
7 Saidpur STP Project             184.93 M/s UEM NGRBA   Contract Agrement is signed on 31.3.2017
8 Saidpur Sewerage Network Project             268.63   NGRBA   LOA issued. Agreement is yet to be done
9 Karmalichak 37 MLD STP               77.04 M/s Voltas NGRBA   Contract Agrement is signed on 31.3.2017
  RIVER FRONT DEVELOPMENT PROJECTS        
1 River Front Development Project - Patna             262.77 M/s. L&T Construction NGRBA 68% To be completed in June 2017
  STORM WATER DRAINAGE PROJECTS        
1 Storm Water Drainage - Phulwarisharif               10.41 M/s Charith Infra Pvt. Ltd. STATE 75% To be completed in 30 April 2017
  SOLID WASTE MANAGEMENT PROJECTS        
1 Waste to Energy Project - Patna   M/s Sunil Hi Tech PPP MODE In progress Handling of MSW at Ramchak Baria
  BUS STAND PROJECTS        
1 Inter State Bus Terminus Project, Patna             331.00 M/s Shapoorji Pallonji and Company Pvt Ltd. STATE   Work yet to be started
2 Darbhanga Nagar Nigam                 3.46 M/s Sharda Construction STATE 60% To be completed in 31 August  2017
3 Saharsha Nagar Parishad                 4.00 M/s Balram Singh STATE 45% To be completed in 30 December 2017
4 Madhepura Nagar Parishad                 4.00 M/s Devraha Const. Pvt. Ltd. STATE 40% To be completed in 30 December 2017
5 Areraj Nagar Panchayat                 1.59 M/s Nityanand Singh STATE 40% To be completed in August 2017
6 Malsalami (Patna Nagar Nigam)                 4.99 M/s Archana Construction STATE 35% To be completed in August 2017
7 Jhajha Nagar Panchayat                 1.82 M/s Lal Rupak Singh STATE 25% Work in Progress
8 Sasaram Nagar Parishad                 3.88 M/s Arun Kumar Singh STATE 20% To be completed in 31 December 2017
9 Ara Nagar Nigam                 4.99 M/s Manoj Kumar STATE 15% Work in Progress
10 Daudnagar Nagar Panchayat                 1.57 M/s S.N. Construction STATE 10% Land dispute
11 Nokha Nagar Panchayat                 2.00 M/s Rita Devi  STATE 10% Land dispute
12 Aurangabad Nagar Parishad                 4.00 M/s Mateshwari Construction STATE   Land Dispute
13 Manpur (Gaya Nagar Nigam)                 6.43 M/s Jai Mata Di Road Construction STATE   NOC not available
14 Motipur Nagar Parishad                 2.00 M/s Ganpati STATE   NOC Not Received
15 Bhagalpur Nagar Nigam                 7.91 M/s Lalan Kumar STATE   NOC not available
16 Sultanganj Nagar Parishad                 2.81 M/s Jai Mata Di STATE   NOC Not Received
17 Purnia Nagar Nigam                 4.99 M/s Umakant Singh STATE   Land not available
18 Chakia Nagar Panchayat                 2.00 M/s Sri Keshew Kumar Keshri STATE   Work Not Started
19 Navinagar Nagar Panchayat                 1.99 M/s Mukesh Kumar Singh STATE   Not started due to local dispute.
20 Nawada Nagar Parishad                 4.00 M/s Jai Mata Di Road Construction STATE   NOC not available
21 Sahebgunj Nagar Panchayat                 2.00 M/s Jagdamba Enterprises STATE   NOC Not available
  BUS PURCHASE PROJECTS        
1 Purchase of 300 Buses for Patna and Bodhgaya               43.60 M/s Maurya Motor Ltd. JnNURM   141 Buses handed over to BSRTC
2 Purchase of 798 Buses for 17 Urban Clusters             112.37   JnNURM    
  OTHER PROJECTS        
2 Rajiv Awash Yojna               16.02 M/s Balaji Enterprises RAY 15% Block-A (24 Dwelling Units)  Completed in 30 September 2017

Block-B  (28 Dwelling Units) Completed in 30 March 2018
  ADB PROJECTS        
1 Bhagalpur Water Supply             493.00 M/s Pan India - Ranhill ADB   To be completed in  year 2022 