SIU Name o project Approved Cost (Rs. Cr.) Agency Time Line Project Completion Date unding Source Amount in BUIDCo (Rs. Cr.) Expense (Rs. Cr.) Physical Status (in %)
1 Buddha Smriti Park 130.94 Pashwanath Developers 9 months 31.12.2012 State Plan 31.91 32.02 Work in progress
Nooranibagh Park, Patna 0.80 Archana Constructions 05 months 23.05.2012 State Plan 0.80 0.54 Complete
Patna Water Supply Project 426.98 Gammon-Geo Miller 24 months 28.03.2014 JNNURM + State Plan 104.46 49.69 4.65
Shaheed Veer Kunwar Singh Azadi Park, Patna 2.00 Archana Constructions 04 months 17.05.2013 State Plan 2.49 0.21  
2 Khagaul Water Supply Project 13.15 JP Enterprises 12 months 28.12.2012 JNNURM 4.63 4.62 19.89
Danapur Water Supply Project 68.96 VISHWA-BRCCPL(JV) 21 months 26.09.2013 JNNURM 25.86 13.53 7.87
Phulwari Water Supply Project 24.70 JP-SMS (JV) 15 months 21.03.2013 JNNURM 9.26 7.01 16.37
PUA Solid Waste Management 11.56 Ramky Enviro Engineers Ltd. Continuous Continuous JNNURM 4.34 3.37 Complete
Bakhtiyarpur Road with Drainage Project 5.11 JMD Road Constructions Pvt. Ltd 6 months 24.01.2012 UIDSSMT 4.03 2.23  
Kankarbagh Park, Patna 0.65 JMD Road Constructions Pvt. Ltd. 12 months 19.11.2012 State Plan 0.65 0.65 Complete
Naubatpur Water Supply 9.89       State Plan 9.89   Tender Phase
Murliganj Road with Drainage Project 11.44 M/SBaba Hans Constructions pvt. Ltd. 9 months 01.03.2012 UIDSSMT 10.96 3.86  
3 Hajipur Sewerage Project 113.62 Tri-Tech Inrastructure 24 months 14.12.2013 NGRBA 20.87 17.68 Nil
Park Shastrinagar Patna 0.85 JMD Road Constructions Pvt. Ltd 9 months 20.07.2012 State Plan 0.85 0.78 Complete
Rajgir Drainage Project 77.67 M/s APR project Pvt. ltd. &  Ramky Inrastructure Ltd. (IV) 12 months 15.12.2012 State Plan 33.10 26.04 27.30
Rajgir Sewerage Project Krushi Inrastructure Pvt. Ltd. 9 months 15.12.2012 State Plan 15.37
4 Bodhgaya Water Supply Project 33.56 SMC - JIT (JV) 15 months 28.03.2013 JNNURM 10.07 8.15 16.07
Bodhgaya Sewerage Project 95.94 Ramky Inrastructure Ltd. 24 months 26.12.2013 JNNURM 28.79 28.35 13.73
5 Begusarai Sewerage Project 65.40 Tri-Tech Inrastructure 24 months 14.12.2013 NGRBA 8.64 9.05 Nil
Munger Sewerage Project 187.89 IVRCL - HDO - KMB 24 months 01.04.2014 NGRBA 35.41 12.55 Nil
6 Jhanjharpur Water Supply 4.94       State Plan 1.60   Tender Phase
Muzaarpur Water Supply Project 98.72 IVRCL 24 months 26.12.2013 UIDSSMT 49.36 11.29 7.45
7 Ara Solid Waste Management Project 9.84 Ramky Inrastructure Ltd. Continuous Continuous UIDSSMT 9.80 2.09 Complete
Buxar Sewerage Project 74.95 Tri-Tech Inrastructure 24 months 14.12.2013 NGRBA 6.63 5.64 1.02
8 Narkatiyaganj Road with Drainage Project 47.13 M/S Baibhav Construction pvt. Ltd. 9 months 23.12.2012 UIDSSMT 22.71 13.96 29.10
Rosera Road with Drainage Project 29.21 M/S Baibhav Construction pvt. Ltd. 9 months 15.12.2012 UIDSSMT 14.07 11.06 46.50