SIU |
Name o project |
Approved Cost
(Rs. Cr.) |
Agency |
Time Line |
Project Completion Date |
unding Source |
Amount in BUIDCo (Rs. Cr.) |
Expense
(Rs. Cr.) |
Physical Status
(in %) |
1 |
Buddha Smriti Park |
130.94 |
Pashwanath Developers |
9 months |
31.12.2012 |
State Plan |
31.91 |
32.02 |
Work in progress |
Nooranibagh Park, Patna |
0.80 |
Archana Constructions |
05 months |
23.05.2012 |
State Plan |
0.80 |
0.54 |
Complete |
Patna Water Supply Project |
426.98 |
Gammon-Geo Miller |
24 months |
28.03.2014 |
JNNURM + State Plan |
104.46 |
49.69 |
4.65 |
Shaheed Veer Kunwar Singh Azadi Park, Patna |
2.00 |
Archana Constructions |
04 months |
17.05.2013 |
State Plan |
2.49 |
0.21 |
 |
2 |
Khagaul Water Supply Project |
13.15 |
JP Enterprises |
12 months |
28.12.2012 |
JNNURM |
4.63 |
4.62 |
19.89 |
Danapur Water Supply Project |
68.96 |
VISHWA-BRCCPL(JV) |
21 months |
26.09.2013 |
JNNURM |
25.86 |
13.53 |
7.87 |
Phulwari Water Supply Project |
24.70 |
JP-SMS (JV) |
15 months |
21.03.2013 |
JNNURM |
9.26 |
7.01 |
16.37 |
PUA Solid Waste Management |
11.56 |
Ramky Enviro Engineers Ltd. |
Continuous |
Continuous |
JNNURM |
4.34 |
3.37 |
Complete |
Bakhtiyarpur Road with Drainage Project |
5.11 |
JMD Road Constructions Pvt. Ltd |
6 months |
24.01.2012 |
UIDSSMT |
4.03 |
2.23 |
|
Kankarbagh Park, Patna |
0.65 |
JMD Road Constructions Pvt. Ltd. |
12 months |
19.11.2012 |
State Plan |
0.65 |
0.65 |
Complete |
Naubatpur Water Supply |
9.89 |
|
|
|
State Plan |
9.89 |
|
Tender Phase |
Murliganj Road with Drainage Project |
11.44 |
M/SBaba Hans Constructions pvt. Ltd. |
9 months |
01.03.2012 |
UIDSSMT |
10.96 |
3.86 |
|
3 |
Hajipur Sewerage Project |
113.62 |
Tri-Tech Inrastructure |
24 months |
14.12.2013 |
NGRBA |
20.87 |
17.68 |
Nil |
Park Shastrinagar Patna |
0.85 |
JMD Road Constructions Pvt. Ltd |
9 months |
20.07.2012 |
State Plan |
0.85 |
0.78 |
Complete |
Rajgir Drainage Project |
77.67 |
M/s APR project Pvt. ltd. &Â Ramky Inrastructure Ltd. (IV) |
12 months |
15.12.2012 |
State Plan |
33.10 |
26.04 |
27.30 |
Rajgir Sewerage Project |
Krushi Inrastructure Pvt. Ltd. |
9 months |
15.12.2012 |
State Plan |
15.37 |
4 |
Bodhgaya Water Supply Project |
33.56 |
SMC - JIT (JV) |
15 months |
28.03.2013 |
JNNURM |
10.07 |
8.15 |
16.07 |
Bodhgaya Sewerage Project |
95.94 |
Ramky Inrastructure Ltd. |
24 months |
26.12.2013 |
JNNURM |
28.79 |
28.35 |
13.73 |
5 |
Begusarai Sewerage Project |
65.40 |
Tri-Tech Inrastructure |
24 months |
14.12.2013 |
NGRBA |
8.64 |
9.05 |
Nil |
Munger Sewerage Project |
187.89 |
IVRCL - HDO - KMB |
24 months |
01.04.2014 |
NGRBA |
35.41 |
12.55 |
Nil |
6 |
Jhanjharpur Water Supply |
4.94 |
|
|
|
State Plan |
1.60 |
|
Tender Phase |
Muzaarpur Water Supply Project |
98.72 |
IVRCL |
24 months |
26.12.2013 |
UIDSSMT |
49.36 |
11.29 |
7.45 |
7 |
Ara Solid Waste Management Project |
9.84 |
Ramky Inrastructure Ltd. |
Continuous |
Continuous |
UIDSSMT |
9.80 |
2.09 |
Complete |
Buxar Sewerage Project |
74.95 |
Tri-Tech Inrastructure |
24 months |
14.12.2013 |
NGRBA |
6.63 |
5.64 |
1.02 |
8 |
Narkatiyaganj Road with Drainage Project |
47.13 |
M/S Baibhav Construction pvt. Ltd. |
9 months |
23.12.2012 |
UIDSSMT |
22.71 |
13.96 |
29.10 |
Rosera Road with Drainage Project |
29.21 |
M/S Baibhav Construction pvt. Ltd. |
9 months |
15.12.2012 |
UIDSSMT |
14.07 |
11.06 |
46.50 |